Judging by shows on DIY Network and HGTV, it takes approximately 24 minutes to renovate a house.

We all know this is not true. But this style of fast-shot remodeling presided over by glib hosts takes away from the core notion that home renovation is complex and difficult and real.

Following is the approximate process for whole-house renovation.

1. Design and Planning
A sketch on a cocktail napkin, full-blown architectural plans, or just a firm set of thoughts about how the remodel should progress. It is cheaper and less frustrating to correct mistakes before the remodel takes physical form.Ensure that you have funding for your renovation and the right materials which inĀ reviewbrewery you can find great reviews.

Draw up a simple “yes/no” list of do-it-yourself projects and projects you want professionals to do.
Look for contractors and subcontractors for those jobs you do not want to do yourself.
Apply for permits.

2. Roof, Foundation, Water Issues, Siding, Windows
Roof replacement or repair; foundation fix; stopping water infiltration; installing or repairing siding and windows. Large projects must be done first because subsequent projects are impacted by them.

Protect your future renovation work by making certain the house won’t collapse on you (foundation, major structural problems) and that it will remain dry (roof, siding, windows).
Secure the foundation.
Make major foundation repairs to areas such as weakened walls, joists, and carrying beams.
Repair or replace the roof.
Replace seriously damaged windows that may threaten future remodeling work. If not seriously damaged, leave it for later in the process.
If the siding is so damaged that it will allow water infiltration, repair or replace the siding. If not seriously damaged, leave it for later in the process.

3. Demolition
Demolishing and disposing of sections of the house that will be replaced by later projects.

Rent a large container for waste.
Carefully demolish all or some of the areas of the house that will be renovated. Demolish as much as possible if you will not be living in the house.
Exercise caution when demolishing surfaces coated with lead-based paint.
4. Structural Carpentry
Carpentry that is in support of other work such as drywall, new or moved walls, windows, doors, etc.

Moving walls.
Constructing new walls.
Significantly enlarging the window openings.
Adding beams to support a greater weight upstairs.
Punching in new doors (or removing existing doors).
Adding new construction windows.
5. HVAC Ductwork, Electrical, and Plumbing
Vital services that need to be installed when the walls and ceiling are open.

With the walls and ceiling open, it is time for the HVAC company to install ductwork for central heating and air conditioning.
Run new electrical and plumbing systems. Electrical and plumbing inspectors will visit at this time, too.
6. Insulation
Laying the insulation in the walls and ceiling.

Install fiberglass insulation in the walls and attic.
Insulation goes fast, so make sure that your drywall company is ready to go soon after this.
7. Drywall
Closing up the walls with drywall: hanging it, mudding it, and sanding it.

A second inspection from the electrical inspector (and perhaps the plumbing inspector) will give you the go-ahead to close up the walls.
Drywallers hang sheets of drywall, apply drywall compound, and let the compound dry. After drying, they sand it smooth. Sometimes, they will repeat the process until they achieve a seamless surface.
8. Windows
Installing new-construction or replacement windows.

Window installation, whether whole-house or partial, almost always plays into a home remodel project.
9. Fine Carpentry
Carpentry that is not supportive: baseboards, molding, trim around windows and doors, built-in elements (bookcases, breakfast nooks, etc.).

Fine carpenters give your house that finished touch.
10. Interior Painting, Wallpaper, and Other Surface Finishes
Painting interior walls, hanging wallpaper, painting molding and trim, staining and sealing trim.

All of these detail-oriented surface finishes should be one of the last items you do indoors as this work can damage other work of yours.
Should you paint before installing or sanding your flooring or the reverse? This is debatable. Laying flooring first means that paint might get on the flooring. Painting first means that the floor sander may scuff your walls.
11. Flooring
Your final floor covering–laminate, solid hardwood, tile, engineered wood.

Installing the flooring as late as possible in the renovation process saves your flooring surface from significant damage.
12. Siding, Gutters
Exterior work on the outside of the house.

With the house mostly finished, it is safe to put on the siding. You do not want to do this earlier (unless absolutely necessary) because doors and windows may get punched out, ruining the siding.
13. Major Auxiliary Building
Any buildings that are detached from the main house.

Additions
Sunrooms
Swimming pools

Customer Testimonials

"Phil was on-site every day and he was very accommodating in letting us into the house to see the progress any time we wanted. I would definitely refer Stevens Builders to my friends."

Suzanne Harutunian

Know Your Builder

top 5 things to know about your builder

Certified Green Professionals

green building

Equal Housing Opportunity

equal housing opportunity

Contact Information

Stevens Builders
Maryland Home Builders
4829 Ten Oaks Road
Dayton, MD 21036 Phone: 410-984-5393